Government of Saskatchewan ministries, Crown corporations and organizations are implementing contingency plans to minimize the impacts of postal service disruption.

Les ministères, sociétés d’État et organismes du gouvernement de la Saskatchewan mettent en œuvre des plans d’urgence visant à réduire les répercussions de l’interruption du service des postes.

Google Translate Disclaimer

A number of pages on the Government of Saskatchewan's website have been professionally translated in French. These translations are identified by a yellow box in the right or left rail that resembles the link below. The home page for French-language content on this site can be found at:

Renseignements en Français

Where an official translation is not available, Google™ Translate can be used. Google™ Translate is a free online language translation service that can translate text and web pages into different languages. Translations are made available to increase access to Government of Saskatchewan content for populations whose first language is not English.

Software-based translations do not approach the fluency of a native speaker or possess the skill of a professional translator. The translation should not be considered exact, and may include incorrect or offensive language. The Government of Saskatchewan does not warrant the accuracy, reliability or timeliness of any information translated by this system. Some files or items cannot be translated, including graphs, photos and other file formats such as portable document formats (PDFs).

Any person or entities that rely on information obtained from the system does so at his or her own risk. Government of Saskatchewan is not responsible for any damage or issues that may possibly result from using translated website content. If you have any questions about Google™ Translate, please visit: Google™ Translate FAQs.

Saskatchewan Hospital North Battleford Audit Released

Released on September 4, 2020

The Government of Saskatchewan today released the third party independent audit of the Saskatchewan Hospital North Battleford (SHNB) facility, and is acting on recommendations to repair identified deficiencies and strengthen governance and processes.

“Government initiated this independent audit to fully understand the state of the facility to ensure the safety of patients, staff and families,” Central Services Minister Ken Cheveldayoff said.  “The audit is a snapshot in time that provides a foundation to address any deficiencies at no cost to government under the unique protections provided through the Public-Private-Partnership (P3) Project Agreement.”

Following a Request for Proposals (RFP) process, JPH Consulting was selected to conduct a construction audit of the quality of materials, equipment, labour and workmanship during the construction phase, and a review of processes used during design, construction and operating periods to examine their adherence to the P3 Project Agreement between Access Prairies Partnership (APP) and the Government of Saskatchewan.

The construction audit identified a range of construction-related deficiencies and issues, and noted the majority of items are not unexpected in a facility of this size.  The audit also states the facility’s construction generally meets the requirements set out in the Project Agreement.

Central Services is working with APP to address items, giving priority to ensure compliance with building code, fire code and safety requirements.

“Ensuring the safety of the patients and staff at the Saskatchewan Hospital North Battleford has always been and continues to be our priority,” Graham Capital President and owner of APP and Graham’s Chief Financial Officer Tim Heavenor said.  “This facility has had its challenges, many of which have already been resolved at no cost to the people of Saskatchewan.  We are committed to addressing the remaining issues outlined in the audit report, so that patients and staff can continue to deliver and receive treatment in a modern mental health facility.”

The process evaluation noted that while commissioning and quality assurance plans were in place to guide the construction phase, the plans were not fully implemented due to unclear roles and responsibilities.  As well, formalized approval and other processes were not consistently followed in accordance with the Project Agreement resulting in some gaps in record-keeping documentation.

“This complex project did have challenges and we have learned from this experience that while we have solid plans in place, we need stronger governance to ensure the plans and formal processes are strictly followed,” Minister Responsible for SaskBuilds Gordon Wyant said.  “These learnings will be applied to future projects, including traditional and P3 builds.”

The audit report is available at https://www.saskatchewan.ca/government/government-structure/ministries/central-services.

-30-

For more information, contact:

Alyssa Pittet
Central Services
Regina
Phone: 306-787-4460
Email: alyssa.pittet@gov.sk.ca