A weekly highway construction update is published throughout the spring and summer months to provide you with a snapshot of the latest construction information.
Please drive safely and obey all highway construction signage.
If you're planning to travel, check the Highway Hotline, which provides up-to-date information on construction, emergency road closures, the status of ferries and barges, and other road activities. Information is also available by calling 511.
New Work | ||||||
Highway | Location | Distance | Description | Estimated Cost | Impact on Motorists | Estimated Completion |
106 | Jan Lake Access | 3 km | Grade raise and seal coat | $3.4M | Watch for people and equipment working | Oct 2024 |
Previous Work | ||||||
1, 4, 11, 13, 44 | Moose Jaw, Swift Current, Dundurn, Shaunavon and Loreburn |
N/A | Install culverts at various locations. | $1.8M | Reduce speed, watch for people and equipment working. | Jun 2024 |
1, 4, 16, 33, 39, 379 | Gull Lake, Wymark, Cadillac, Springside, Pilot Butte, Regina, Kronau, Rouleau, Wilcox, Lang, Yellow Grass, and Weyburn | 147 km | Crack sealing on various sections of highways. | $1.7M | Reduce speed, watch for people and equipment working. | Sep 2024 |
1, 6, 11, 16 | Aylesbury, Churchbridge, Craik, Grenfell, Guernsey, Humboldt, Indian Head, Lestock, MacDowall, Mortlach, Parry, Rein, Waldeck, and Yorkton | 670 km | Paving on various sections of highways. | $12.1M | Speed reduced to 60km/h. One lane traffic, flagpersons, watch for people and equipment working. | Sep 2024 |
1, 8, 13, 38, 247 | Moosomin, Kelvington, Kamsack, Carlyle, and Stockholm | N/A | Install culverts at various locations. | $2.7M | Reduced speed with traffic delays, watch for flagpersons. | Aug 2024 |
1, 13, 37, 47, 48 | Indian Head, Rush Lake, Gull Lake, Eastend, Shaunavon, Grenfell and Windthorst | 257 km | Seal coating on various sections of highways. | $7.5M | Speed reduced to 60 km/h. Flagpersons and pilot vehicles will guide traffic through the work zone. | Jun 2024 |
1, 47 | Grenfell, Broadview | 32 km | Paving on Hwy 1 near Broadview in both lanes and north intersection of Hwys 1 and 47 | $10.5M | Slow to 60km/h within the work zone. Watch for equipment and people working. One lane traffic and restricted lane width to 3.7 m | Oct 2024 |
2, 3, 265, 355 | Christopher Lake, Melfort, Prince Albert, and Candle Lake | 80 km | Crack sealing on various sections of highways. | $1M | Speed reduced to 60km/h. One lane traffic, flagpersons, watch for people and equipment working. | Jun 2024 |
2, 18, 28 | Scout Lake, Climax, Trossachs | N/A | Install culverts at various locations. | $1.5M | Reduce speed, watch for people and equipment working. | Oct 2024 |
2, 18, 377 | Rockglen, Bracken and Radville | N/A | Install culverts at various locations. | $1.8M | Reduced speed limits with brief stops, one-way traffic controlled by signal lights. | Sep 2024 |
2, 20, 368 | Watrous, Lanigan and St. Brieux | 194 km | Seal coating on various sections of highways. | $9.4M | Reduced speed, one-lane traffic, pilot vehicles, lane width restricted to 4 m. Be prepared to stop. Watch for fresh oil, loose stones and dust. | Sep 2024 |
3 | Kinistino | N/A | Install culvert to replace an existing small bridge. | $845,000 | Reduce speed, watch for people and equipment working. | Oct 2024 |
3, 23, 55 | Nipawin, Carrot River and Birch Road | 40 km | Paving between Nipawin and Carrot River. | $20.4M | Reduce speed, watch for people and equipment working. | Oct 2024 |
5 | St. Denis | 17.5 km | Build two passing lanes, widening, and two intersection safety improvements between Hwy 2 and Blucher Rd. | $40.3M | Slow to 60 km/h, watch for people and equipment working. Alternate route available. | Oct 2024 |
5 | Kuroki | N/A | Culvert Installation | $470,000 | Reduce speed, watch for people and equipment working. | Jul 2024 |
6 | Regina | N/A | Install culvert north of Grid Road 734. | $444,000 | Reduce speed, watch for people and equipment working. | Jul 2024 |
6 | Gronlid | N/A | Slideslope and erosion repairs along Saskatchewan River valley, George Willis Bridge and Wapiti Valley Regional Park | $5.7M | Reduce speed, watch for people and equipment working. | Jun 2024 |
6, 39 | Rowatt and Corinne | 27.8 km | Twinning sections of highway. | $49M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
7 | Kindersley | N/A | Safety improvements at intersections with Ditson Dr and Hwy 21 in Kindersley. | $6.3M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
7, 378 | Rosetown, Kindersley and Spiritwood | N/A | Install three culverts. | $980,000 | Reduce speed, watch for people and equipment working. | Jun 2024 |
8 | Rocanville | 14.6 km | Paving on Nutrien Mine Access Road. | $11M | Be prepared to stop, reduced speed, restricted lane width, watch for people and equipment working. | Oct 2024 |
8 | Spy Hill | 15.5 km | Paving south of Spy Hill. | $7.5M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
8, 11, 304 | Rocanville, Craik and Makwa |
N/A | Install culverts at various locations. | $2M | Reduced speed limits with occasional brief stops. | Jun 2024 |
9 | Whitewood | 19.5 km | Paving and grading north of Hwy 1 to near the Richardson Pioneer Access. | $7.8M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
9 | Whitewood | 14.7 km | Paving south of Whitewood. | $2.5M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
9, 11, 16, 35, 304 | Endeavour, Hague, Viscount, Archerwill, Saskatoon, and Makwa | 148 km | Seal coating on various sections of highways. | $5.2M | Speed reduced to 60 km/h. Flagpersons and pilot vehicles will guide traffic through the work zone. | Sep 2024 |
9, 15, 22, 310, 364 | Yorkton, Melville, Goodeve, Gerald, Ituna, and Balgonie | 191 km | Seal coating on various sections of highways. | $8.5M | Reduce speed, watch for people and equipment working. | Sep 2024 |
11 | Floral Road, Saskatoon | 1 km | Safety Improvements | $6M | Reduce speed, watch for people and equipment working. | Jul 2024 |
11, 12 | Saskatoon | 17 km | Paving north of 71 St in Saskatoon. | $7.3M | Slow to 60 km/h, watch for people and equipment working. | Jun 2024 |
15 | Kenaston | 22 km | Paving and subgrade improvements. | $22M | Slow to 60 km/h, watch for people and equipment working. | Nov 2024 |
15 | Outlook | 11.4 km | Paving east of Hwy 42. | $6.2M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
15, 16, 219 | Broderick, Maymont, and Cutbank | N/A | Install culverts at various locations. | $1.2M | Reduce speed, watch for people and equipment working. | Jun 2024 |
16 | Radisson | 18.5 km | Paving eastbound lanes west of the Borden Bridge to Hwy 340. | $10.6M | Slow to 60km/h, watch for people and equipment working. | Oct 2024 |
16 | Yorkton | 24 km | Paving between Hwys 80 and 9 and in Yorkton. | $10.3M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
21 | Toby Nollet Bridge | 15 km | Paving of truck climbing lanes | $7.5M | Reduce speed, one lane traffic, watch for people and equipment working. | Jun 2024 |
22 | Esterhazy | 1.2 km | Paving and widening four intersections near Esterhazy. | $2.1M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
26 | Goodsoil, Loon Lake | 25 km | Paving on Hwy 26 north of Hwy 304, north of Hwy 55 to Hwy 954 and in Greig Lake Provincial Park. | $17M | Currently no restrictions. | Jun 2024 |
35 | Qu’Appelle | 19.7 km | Paving on Hwy 35 from Hwy 1 through Town of Qu’Appelle to Hwy 10. | $4.3M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
37 | Gull Lake | 1.3 km | Paving and reconstruction through Gull Lake including new curbs and gutters. | $5M | Detour in effect. | Oct 2024 |
40 | Battleford | N/A | Install culvert west of Battleford. | $1.8M | Slow to 60 km/h, watch for people and equipment working. | Jun 2024 |
80 | Churchbridge | N/A | Culvert installation | $586,000 | Detour in effect | Sep 2024 |
123 | Tobin Lake | 4 km | Grading on various sections. | $4.2M | Slow to 60 km/h. Watch for equipment and people working. | Jun 2024 |
155 | Buffalo Narrows | 28 km | Paving | $17.4M | Watch for people and equipment working | Oct 2024 |
305 | Dalmeny | 11.5 km | Paving, realignment and subgrade improvement near Langham and Dalmeny. | $13M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
312 | Rosthern | 12 km | Paving from Hwy 11 intersection to 12 km east | $8.3M | Reduce speed, watch for people and equipment working. | Oct 2024 |
335 | Carrot River/Gronlid | 0.9 km | Erosion repairs and retaining wall | $1.3M | Reduce speed, watch for people and equipment working. | Oct 2024 |
397 | Allan | 13 km | Paving near Allan between Hwys 397 and 16 and the Elstow access. | $8.3M | Slow to 60 km/h, watch for people and equipment working. | Oct 2024 |
924 | Sled Lake | 21 km | Grading | $9.8M | Slow to 60 km/h One way traffic, reduced lane widths, expect delays | Aug 2024 |